Sunday, May 27, 2007

Site visit 3

Ryrie St, Geelong 20/05/07
In this photo we can see concrete columns and steel universal
beams. Condek is getting laid on the upper beams for what will
become the third storey. After the condek is laid it will be filled
will concret to form the floor of that level.
Here we can see the fire services and mechanical ducts.
Here we can see the partially completed timber formwork for a set
of concrete stairs. The steel reinforcement is in place and soon the
concrete will be poured and the stairs complete.

This section of formwork over the stairway has already had its
concrete pour. It has set and the builders have started to remove
the formwork.